Reeds Mill Sewage Pump Station Rehabilitation Project
Reeds Mill, Wintersville
UPDATES AS OF JANUARY 2024:
Construction on Reeds Mill Pump Station Rehabilitation Project is fully complete. Everything is operational and functioning as indented, pumping sewage to one of the JCWSD’s treatment plant.
UPDATES AS OF MARCH 2023:
Construction on Reeds Mill Pump Station Rehabilitation Project is ongoing. The new electrical building, electrical components, pumps, valve vaults, and force mains have been installed. The pump station is currently operating while misc. pieces of equipment arrive on site. The project is set to continue through the spring of 2023.
UPDATES AS OF JUNE 2022:
Construction on Reeds Mill Pump Station Rehabilitation Project will occur in the summer of 2022.